Baumit Nivello 50, 25 kg – Cement-Based Self-Levelling Floor Compound for Layers from 2 to 50 mm
Baumit Nivello 50 is used to level floors before installing tiles, parquet, PVC flooring or other floor coverings. Its 2 to 50 mm application range is particularly useful when renovating rooms with uneven subfloors. You can apply a thin layer over high spots and fill deeper areas to bring the surface up to the required level. Before starting, measure the difference between the highest and lowest points to check whether the planned finished floor height allows the levelling layer to stay within the specified thickness range across the entire area.
The cement-based compound contains fine sands and additives. Once mixed with water, it is poured onto the prepared subfloor and levels itself after spreading and removal of entrapped air. It is suitable for floors with underfloor heating and for sheltered, covered outdoor areas. When tiling outdoors, apply a waterproofing layer over the levelled surface before laying the tiles.
When to Use Baumit Nivello 50
- Before laying ceramic or porcelain tiles – to correct uneven areas and provide a flat surface for tiling.
- Before installing parquet or other timber flooring – to level the subfloor. Check that the residual moisture is within the flooring manufacturer's limit before installation.
- Under PVC flooring and textile coverings – where a smooth substrate is needed because ridges and depressions can show through thin coverings.
- Under epoxy coatings – provided the substrate preparation and moisture requirements of the chosen coating system are met.
If floor height is limited, check door clearances and transitions to adjoining rooms. When calculating the finished floor height, allow for the thickness of the levelling layer, the floor covering and any adhesive or underlay.
Technical Specifications
| Property | Value |
| Bag size | 25 kg |
| Layer thickness | 2–50 mm, with a minimum of 5 mm over suitable timber substrates |
| Approximate consumption | 1.6 kg/m² per mm of layer thickness |
| Water per bag | Approximately 5.25 L. Mixing range: 5.0–5.5 L |
| Working time at +20 °C | Approximately 30–35 minutes |
| Ready for foot traffic | After approximately 3 hours |
| Classification to BDS EN 13813 | CT-C30-F6 |
| Tensile bond strength on concrete | Greater than 1.5 N/mm² |
| Reaction to fire | A1 |
| Emissions classification | EMICODE EC 1 PLUS |
| Temperature during application and setting | Above +5 °C and up to +30 °C for the air, material and substrate |
| Pallet quantity | 54 bags, 1,350 kg total |
| Storage | Approximately 9 months in dry conditions, on wooden supports and under protective wrapping |
How Many Bags Do You Need?
Multiply the floor area in square metres by the average layer thickness in millimetres and then by 1.6. Add approximately 10% as an allowance, divide by the 25 kg bag weight and round up to the nearest whole bag. For uneven floors, measure the required thickness at several points. If one area is deeper, you can calculate the quantity for that area separately.
| Average layer thickness |
Consumption per m² |
Coverage per bag before allowance |
| 2 mm | 3.2 kg | Approx. 7.8 m² |
| 5 mm | 8 kg | Approx. 3.1 m² |
| 10 mm | 16 kg | Approx. 1.6 m² |
| 20 mm | 32 kg | Approx. 0.78 m² |
| 50 mm | 80 kg | Approx. 0.31 m² |
Example for a 12 m² room with an average layer thickness of 5 mm. The estimated requirement is 96 kg, or 105.6 kg with a 10% allowance. Allow five 25 kg bags for this floor. Actual consumption depends on the surface profile, substrate absorbency and application method.
Suitable Substrates and Preparation
Nivello 50 can be applied to sound mineral substrates, including concrete and cement, gypsum or asphalt screeds. The substrate must be dry, load-bearing and free from frost. Remove dust, grease and any loose or crumbling material. Use Baumit Grund on absorbent substrates or Baumit SuperPrimer on non-absorbent substrates. Plastic and metal are unsuitable substrates.
On timber subfloors, check that the boards or panels are securely fixed. The substrate must be stable and free from movement or vibration. After sanding and removing dust, apply a compatible epoxy primer such as Murexin EP 170. Once it has cured, apply Baumit SuperPrimer and let it dry before pouring the levelling compound. The minimum layer thickness over timber is 5 mm.
Carry existing expansion, movement and perimeter joints through the levelling layer. Keep the joints clear of compound while pouring. For layers 5 mm or thicker, fit a perimeter isolation strip along adjoining walls.
Mixing and Application
- Measure the water. Use 5.0–5.5 L of clean, cold water per 25 kg of dry compound. Gradually add the powder to the water.
- Mix until uniform. Use a low-speed paddle mixer at up to 600 rpm. Mixing takes approximately 3–5 minutes. At +20 °C, the working time is approximately 30–35 minutes. Discard any compound that has started to set. Use only water for mixing.
- Pour and spread with a levelling rake. Spread the compound to the required thickness and run a spiked roller over the fresh material to release entrapped air. On larger floors, organise the batches so that adjacent pours meet while the material is still fresh. Machine application is also possible using a screw pump with a continuous material feed.
- Protect the fresh layer. Shield it from draughts, direct sunlight and local heat sources. If a second layer is needed, apply it as soon as the first layer can be walked on. If the interval is longer, prime with Baumit Grund before applying the next layer.
When Can You Install the Floor Covering?
Baumit's indicative drying times are based on +20 °C and relative humidity below 70%. Allow approximately 24 hours for a 2 mm layer and approximately 48 hours for layers over 2 mm and up to 10 mm. For thicker layers, allow an additional 12 hours for each millimetre above 10 mm. Lower temperatures and higher humidity can extend drying times.
The approximate 3-hour waiting time applies to foot traffic. For layers over 10 mm or when installing moisture-sensitive flooring, check the residual moisture using the calcium carbide method (CM test) and follow the limit specified by the floor covering manufacturer.
Underfloor Heating and Outdoor Use
For underfloor heating, the substrate must be dry and preheated in accordance with the applicable procedure. Switch the heating off at least 24 hours before applying the compound and wait at least 24 hours after application before switching it back on.
For outdoor use, apply Nivello 50 in sheltered, covered areas. Before laying exterior slabs or tiles, install a waterproofing layer such as Baumit Baumacol Protect. If the floor has a designed fall towards a drain or drainage channel, check how it will be maintained during levelling. The material is frost-resistant and is unsuitable for areas subject to constant or prolonged water exposure, such as swimming pools, water tanks and car washes.